HOME            EXPERIENCE PORTFOLIO            ACCOLADES            NEWS/LINKS            CONTACT US
E D U C A T I O N
Higher Education
>   Fairmont State University - Engineering Technology Annex
>   Westminster College Campus Center
>   Washington & Jefferson - Technology Center
>   Washington & Jefferson - Howard J Burnett Center
>   PITT College of Business Admin. Center for Student Success
>   Robert Morris University - Facilities Service Center
>   Fairmont State University - Inner Campus Center
>   Waynesburg University - Pedestrian Link
>   West Virginia University - Vivarium Expansion
>   West Virginia University Book Depository
>   Robert Morris University - Art Gallery
>   Augusta at Falling Run
>   CCAC North
>   Duquesne University Renovations
     
Libraries
>   Andrew Carnegie Free Library & Music Hall
>   Butler Library
>   Sewickley Library
     
Schools
>   St. Alphonsus Church Addition and Renovations, Gymnasium
>   Mother of Sorrows Parish Addition and Renovations
>   Memorial Park Church Classroom, Office and Daycare Facility
     
FACILITIES SERVICE CENTER
PROJECT: Additions and Renovations
OWNER: Robert Morris University
ARCHITECT: In-house
LOCATION: Moon Township, Pennsylvania

Robert Morris University had a clear vision for their new facilities center. The opportunity to bring that vision to fruition in a cost effective manner presented itself when an existing building very close to the Moon campus became available. After consulting Landau about pricing and scheduling, RMU opted to purchase the property.

The 9,000 SF addition and 25,000 SF renovation was designed, permitted and built in 4.5 months.  There were no formal drawings. In many instances, design happened minutes before construction. The budget and fast track schedule drove the project. There was constant communication and coordination between RMU and Landau. All decisions were made in the owner’s best interest. Where necessary, Landau involved experts to solve unique problems. Alternate construction methods were continuously proposed to achieve RMU’s goals in the most efficient manner.

“The project team worked very well together, meeting at least weekly due to the aggressive Phase I schedule and the fact that the design continued to evolve as construction progressed.”
- Bill Joyce, Robert Morris University Architect




Previous / Next / Portfolio Menu
© 2006-2012 Landau Building Company, All Rights Reserved